[6.17] a

6.17. The impact of any modifications to the design that have been implemented during the excavation and/or construction period should be considered in the safety case and associated safety assessment. This process should be supported by the following:@@- An update of the level of knowledge on the ability of each component of the disposal system to fulfil its expected role under the normal evolution of the facility and under disturbing events, both anticipated events and less likely events. This should include a full scale characterization of the site, the maximum waste inventory for the facility, including radiological characteristics and other properties of the waste, presentation and explanation of design features, where appropriate supported by tests, and demonstrations of prototypes of critical components identified.@@- The choice of construction techniques and their validation, i.e. demonstration that these technique(s) preserve the containment and isolation properties of the natural barriers to the extent necessary.@@- An identification of areas where uncertainties important to safety still exist, which will have to be managed as part of the demonstration of safety.

[6.17] 특정 문제

6.17. 굴착 및/혹은 건설 기간 동안 구현된 설계의 변형에 대한 충격은 반드시 안전사례 및 안전성 평가에서 고려되어야 한다. 이 절차는 다음에 의해 지원되어야 한다. :@@- 개연성 있는 사건 및 개연성이 없는 사건에서 처분시설의 정상적인 전개(진화)에서 충격적인(비정상적인) 사건 발생 시 예상되는 역할을 수행하는 처분시스템의 각 구성요소 기능에 대한 지식수준의 갱신이며 이는 처분시설의 방사선적 특성, 다른 폐기물 특성, 실험에 의해 뒷받침되며, 주요 구성요소에 대해 데모로서 입증이 된 설계 특징에 대한 설명, 방폐물 재고량 목록 및 자세한 부지 특성 자료를 포함해야 한다.@@- 건설 시 선택된 기술과 이에 대한 검증, 예를 들면 필요한 정도로 천연방벽의 밀봉 및 격리를 유지시키는 기술.@@- 안전에 중요한 불확실성이 존재하는 영역의 식별, 즉 안전 입증의 한 부분으로 관리해야 한다.