[2.4] a

2.4. The development of a geological disposal facility is likely to take place over several decades. These long timescales, the large volume of information (to be acquired from site characterization and other activities that will support the safety case) and its diversity make it essential to subdivide the programme into a series of steps so that the work can be performed, reviewed and assessed in manageable ‘'packages’' with the overall objective of exercising proper control throughout the programme. This comprises the step by step process. Operators of geological disposal facilities may define a number of steps in their own programme. However, in this Safety Guide the step by step process refers to the steps imposed by the regulatory and political decision making processes.

[2.4] 심층처분의 개요 및 이행

2.4. 심층처분시설의 개발이 다분히 수십 년 이상 소요될 수 있다. 이러한 긴 시간대와 (부지특성과 Safety Case를 지원하는 기타 활동으로부터 취득되는) 다량의 정보와 이들의 다양성으로 인해 개발프로그램을 일련의 단계로 분할하는 것이 필수적이다. 따라서 해당 프로그램을 통해 적절한 통제의 목적으로 관리가 가능한 “패키지”로서 수행되고, 검토되고, 평가될 수 있다. 이것이 단계별 절차로 구성된다. 심층처분시설의 운영자는 그들의 프로그램에서 많은 단계로 정의할 수도 있다. 그러나 본 안전지침에서 단계별 절차는 규제적 및 정치적 결정절차에 따라 부과된 단계를 의미한다.